Adding months to a date: the end-of-month problem
What is one month after January 31? There are a few answers, and it matters for bills, contracts and subscriptions.
The usual rule
Keep the same day of the month. March 15 plus one month is April 15. If that day doesn't exist in the target month, use the month's last day: January 31 plus one month is February 28 (29 in a leap year).
Why it matters
Adding one month twice is not always the same as adding two months at once: January 31 → February 28 → March 28, but January 31 plus two months is March 31. Subscriptions and loan schedules usually keep the original day where possible.
Days vs months
“30 days” and “one month” are different. A 30-day window from January 31 ends on March 2 (or March 1 in a leap year); a one-month window ends on February 28. Contracts usually say which they mean.